17 August 2023

Then what needs to be done on the ECML and (East) Midlands Main Line (MML) railway.


It has always been said that the line up the east coast of Britain was the better one for connections to Scotland from London. This was put down to the terrain which tended to be flatter than the west coast with the possibilities of more straight stretches of line facilitating the greater possibility of achieving fast speeds. In fact in the 1930s(3rd July 1938), the fastest speed still standing for a steam engine (LNER Mallard), was achieved on this line at 126 mph (203kph). There were also no great lengths of line in England that were impeded by hills and mountains. That was only the case in Scotland where the route had to go more slowly along the coast between Newcastle and Edinburgh.

The WCML has a length of 642kms. which is 10 kms. longer than the ECML but has almost always tended to have more traffic using it, long-distance, commuter rail and freight.  

I cannot give you the length of the whole west coast line from London to Scotland after my proposed new lines,renewals and up-grading. However, I can do so on the length of lines from Lancaster to Glasgow (west coast) and from York to Edinburgh (east coast) which start at roughly the same latitude, 54º02´ versus 53º57´ .

Under my proposals, as seen in my previous article, the west coast line (HS2) from Lancaster to Glasgow would come in at 254.5kms.while the east coast line (HS3) would come in at 286kms. A difference of 31.5kms.That is a very similar distance considering the differences between the routes.

The ECML (East Coast Main Line) was the name given to the main rail route from London Kings Cross to Edinburgh via Doncaster, York, Darlington and Newcastle. However, it cannot be taken in isolation as the East Midlands Line is part and parcel of the same route up to Leeds. It runs through Bedford, Leicester, Loughborough and Chesterfield to Sheffield. Up to the present that is considered the end of the line while logic demands it be extended to Leeds(and/or Bradford). That is not the case because of the atrocious network of railways between Sheffield and Leeds, inherited and never up-dated, from the original constructors in the 19th Century.

 

If the ECML is split in three parts we find that each length comes out as follows....

Kings Cross - York                303kms.     

York - Newcastle                  129kms.

Newcastle - Edinburgh          200kms.

TOTAL  ECML                      632kms.

 

If we look at the up-dated, improved, straightened line, we can call it HS3 (High Speed 3 - as an extension of HS2). Then each length comes out the following way....

Kings Cross - York                297kms.

York - Newcastle                  121kms.

Newcastle - Edinburgh         165kms.

TOTAL HS3                         583kms.

Saving on new route           49kms.

 Let us look at the line in its three stages.

1- Edinburgh - Newcastle

This is the worst part, and slowest because of the terrain.

The present ECML runs along the coast from Edinburgh to Newcastle (white line).Constructing the fast line (HS3 - the blue line) will save 35 kms. on that part of the route, while still avoiding all designated areas of natural beauty. Surely this should be a must in the usually difficult terrain of Scotland. It is shorter, more direct, and with more gradual inclines to pass over the intermediary landscape. A two-track system would be quite sufficient to accommodate High Speed trains, fast freight trains and fast regional trains which could have `passing loops at intermediate stations, such as Newcraighall, Mayfield, Coldstream, Newcastle Airport. These stopping trains would be similar to the Javelin services out of St. Pancras to the Kent coast.  In fact all the HS trains could stop at Newcastle Airport as a matter of course.


  2- Newcastle - York

 The section from Newcastle to York is one of the easier ones to bring up to scratch. The most important part is between the towns of Chester-le-Street and down to Northallerton, or further down to Thirsk. There are some sections which can gain a lot of line speed by straightening. The terrain is no big problem so probably could provide us with two fast tracks within a year. The saving in track distance would be 8 kms. which is not too great but could make a big difference in line speeds.


 

 3)- York - Kings Cross

There are several stretches along this stage which require either, straightening or increasing to four tracks. They are not difficult to achieve as was the line from Newcastle to York. The markers point out the most important sections. The most notorious section, however, is that between Knebworth South and Welwynn Garden City North. It is less than 4.5 kms in length but is a bottleneck. There is no excuse which can justify leaving this problem for so long. Four-tracking the section is a must though somebody will feel badly treated as a result. I do not offer a solution as the people on the ground in that area can perhaps offer better and more satisfactory solutions. I only have to remind you that there are three solutions --- over, under or round --- whichever is the most satisfactory.

The rest of the line into London offers no great problems except for the volume of traffic. This is inevitable in a big city, and might make a new line construction the only solution for future expansion. 

Along the whole section from York to London the distance saved only comes to 6kms. but it would improve the service substantially. 

The (East) Midlands Main Line(MML)

Initially the MML is considered to go from London St.Pancras to Sheffield. It has been electrified to Corby and Market Harborough which are just south of Leicester. Since the whole line is going to be electrified, at some point (we do not know when) we will look at this line from south to north The next stage being electrified is the short section up to Wigston just south of Leicester.

I cannot make much comment on the stage from here to Sheffield as we do not know the specific plans. I can only speculate as I have done on the map. There are various parts where line straightening could be made, especially in the part from Old Whittington (just north of Chesterfield) to Sheffield.

From Sheffield logic dictates that the line continues north from Sheffield to Leeds (and Bradford). As the lines between these cities are very windy I can only propose a solution as shown on the map. This should solve the problem of the slow, windy line, offering a much faster alternative through Barnsley to Wakefield. There one branch would continue to Leeds while another would branch off left to Bradford. I should point out that the section from Wakefield to Leeds would be the same as the one that forms part of the ECML from London Kings Cross to Leeds.


 

These improvements to the ECML/HS3, and the MML are so important yet not so significant in distance or works, that I cannot understand why they have not been attacked before. The gains are tremendous and could alter the balance between west and east to the benefit of the latter -- which is something politicians  have been aiming for during decades. Now is the time to go ahead.

06 June 2023

The Crewe to Manchester fast railway link, and the WCML.

 Tuesday 31st January 2023 the House of Commons debated the Bill permitting the construction of the fast rail link from Crewe to Manchester Piccadilly. This is part of section 2b of the High Speed 2(HS2) line originating in London and initially laid out to Manchester. The line to Crewe has already been decided and is being built.

 This blogger considers that the line, as it is laid out in this last stage from Crewe to Manchester, is grossly damaging to the environment, unnecessary in the majority of its length, prohibitively expensive in its costs, and adds nothing, or very little, of value to the rail system of this country.

 I know that the period for consultation is now closed on discussion of this Bill. That, however, should not be an obstacle to any rectification. The Bill should not take on a life of its own which pushes it forward erroneously. The members of the House of Commons should take the opportunity to reject the Bill in its present form. That way the Department for Transport can offer a new Bill which retains the few good parts of the plan, but eliminates the completely unnecessary, grossly damaging and prohibitively expensive elements.


Let us look at the present proposal as it is shown on the HS2 website.

The title of the image as presented is......

HS2 Crewe to Manchester,   2017 Prefered Route

 

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/630690/C320-AEC-EN-MAP-200-000001_P03_wm.pdf

Unfortunately, this map is out of date, especially since the Golbourne link (from Manchester Airport to  Ashton-in-Makerfield, just south of Wigan) is still shown after it had been cancelled on 6th June 2022. On the map this link refers to sectors HSM12, HSM21, and HSM22.

In the Minister´s statement to Parliament on 6th June 2022....

"Removing the Golborne Link from the HS2 Bill",  (https://www.gov.uk/government/speeches/removing-the-golborne-link-from-the-hs2-bill)

....he basically said that the link did nothing to alleviate capacity limitations on the WCML between Crewe and Preston, so was unnecessary. "He recommended that the government should reduce journey times and increase rail capacity between England and Scotland by upgrading the WCML north of Crewe and by doing more work on options for alternative northerly connections...".

To take this thinking to its conclusion  then we can see that the branch of HS2 in the direction of Manchester Airport as shown on their map is completely unnecessary. That makes it ecologically damaging, and as a result prohibitively and unnecessarily expensive. This would mean that sectors HSM10B and HSM28A are superfluous to requirements. Therefore, these sectors should not be included in the Bill. That means we are left with just sector HSM28B. This is the sector which will pass underground from the Airport to surface at Ardwick before entering Piccadilly.

 This section of HS2 should be retained but with slight modifications. It is a good idea to have a fast, uninterrupted link from Piccadilly to the Airport. However, What is the point of having the Airport station some way from the Airport if this section of the line will go through the station airport. If we follow the thinking as shown on the WCML by upgrading it, then we can do the same on the line from Crewe through Holmes Chapel and Wimslow to enter the Airport, instead of the damaging, expensive and superfluous sectors HSM10B, HSM28A, as well as the cancelled Golbourne link.

Some sectors will need quite extensive upgrading but without doubt the resulting cost will be much lower than constructing new lines in virgin territory. This blogger works on the principle that major lines - such as the WCML, and the connection from Crewe to Manchester Airport should be four-tracked. This means you can separate freight, regional and commuter traffic from High Speed/Inter-City, and fast non-stop services. The only sections where these different sorts of traffic would merge or coincide would be at stations where all the trains stop (except freight).

HSM28B would be the only part of this plan that would be used. Then again it should be pointed out that in the original plan the HS2 Airport station was outside the airport. In the ideas presented here the airport station situated within the airport would be extended westwards to join HSM28B so as to eliminate the need for the station outside.

This map will illustrate what needs to be/can be done.........

 

As can be seen on the map I have illustrated two lines. 

1)- the West Coast Mainline (WCML) from Crewe to Wigan North Western. This follows the line of the existing WCML.

The medium blue line which runs under Crewe and emerges north of the town is common to both WCML and HS2 up to Crewe Central – this would be an underground facility under Crewe Station to be used in case of necessity. Its length is 5.50 kms. and included in WCML

The blue markings indicate where the line is four-track and does not need extensive renovating. There was renovation done on this part of the line in the first decade of the twenty-first Century. I do not know if the signalling system needs an upgrade. There are four sections on which very little or no upgrade work needs to be implemented...........

Crewe North to Winsford South.....................................................8.40 kms.

Hartford  North to South Weaverham............................................2.43 kms.

Manchester Ship Canal to Winwick...............................................8.20 kms.

Golbourne to Wigan North Western..............................................9.20 kms.

TOTAL                                                   28.23 kms

To make all the WCML four-track to the top standard, then those parts indicated in very light blue would need work on them. These break down into three sections.....

a)Winsford South to Hartford North..................................................9.00 kms.

b)South Weaverham to the Manchester Ship Canal ......................13.00 kms.

c)Winwick to Golbourne ...................................................................4.45 kms.

TOTAL                                                   26.45 kms.

a)Only on the first section is tunnelling probably needed to avoid unnecessary disruption, and not on the whole 9 kms.  

b)In the second section there is plenty of land to build new track.                               

c)In this third section a flyover will have to be constructed at Winwick Junction to separate the WCML to Wigan from the connection to the Chat Moss Liverpool to Manchester line at Earlestown.                                     

                             

2)- to differentiate the two examples, I have called the other the HS2 from Crewe to Manchester Piccadilly. The first part through Holmes Chapel (lightish blue) to Manchester Airport follows the line of the existing railway along that route up to the Airport. After that the line would continue non-stop underground out of the west of the airport (darkish blue) and up northwards parallel to the M62 to emerge at Ardwick before entering Piccadilly. The other part would enter the present airport station to connect to the new fast line to Piccadilly but principally continue along the present stopping line to Ardwick and then into Piccadilly (colour purple).

Crewe Central to Crewe North East (also a new underground line - darkish blue)                                             2.00 kms.     

Crewe North East to Manchester Airport (up-grade existing line)  34.50 kms.

Manchester Airport  to Ardwick (new fast underground line)                                                                              14.30 kms. 

Manchester Airport to Ardwick and Piccadilly (via existing line)    14.60 kms.   

 

TOTALS                                    16.30 kms.                                   49.10 kms.  

 


The next logical step in the renovation/updating of the WCML/HS2 line is to look at the two principal obstacles to making it a really fast line in all its length.These are the sections from 

a)Lancaster to Penrith,then

b)from Penrith to Gretna Green and 

c)from Gretna Green to Glasgow.   

a)When I talked initially about the major rail trunk routes, I said that they all should be 4 tracked (and even 6 tracked where it is needed). Looking at the line from Lancaster to Penrith, on reaching Morecambe Bay the line runs at sea level next to the water for a good length. Sea levels rising with the change of climatic conditions and the expectancy of more frequent and more violent storms on stretches open to the sea would make it prudent and foresighted to start elevating the railway on to a viaduct to run behind the houses and not spoil their view of the Bay. This would run to at least Carnforth. The difficulty of incorporating the new fast line into the WCML so as to run through both Carnforth and Oxenholme would suggest that the new two tracks would not run through those stations, but near them.

From Oxenholme onwards the new fast two tracks would be planned towards Penrith more directly by elevating the line on to a viaduct as far as possible until a tunnel is essential. I calculate that at most such a tunnel towards Penrith would be between 10 and 12 kms. long (at an estimated maximum altitude of 300 metres). The whole stretch from Lancaster to Penrith could be reduced by the two new fast tracks from the existing 82.5 kms. to 75.5 kms. The saving in length would be thus 7 kilometres.      

b)The second segment would run from Penrith to Gretna Green a total distance on the WCML of 44.5 kms. HS2 would have to be added to the same track to make it four-tracked. Here the construction is relatively easy since WCML and HS2 could run side by side with the difference that HS2 could avoid some of the (few) curves, be straighter and thus faster. The difference in length is minimal (44 kms.), just 500 metres.

c)The third and longest sector runs from Gretna Green to Glasgow. To sort out the vagaries of the curves and terrain the alignment of the two new fast tracks would be completely new. The length of the WCML along the present line is 150 kms. from Gretna Green to Glasgow. The alignment of the new two-track section is 135 kms. resulting in a saving of 15 kms.   

If we consider the total of the three sections from Lancaster to Glasgow then the distances come out to be......

1) WCML (the actual railway) ............................................................. 277 kms.

2) HS2 (the new railway to be built between the same stations) ........ 254.5 kms.      

The TOTAL saving in length with the new aligment comes out at ......   22.5 kms.

****************************************

 There is one section I have missed out for the line from Crewe to Glasgow and that is the one between Wigan North Western to Preston and Lancaster. Except for the passage through the three stations, where the trains stop to pick up passengers, as is their wont, the 58 kms. line is almost straight along all its length. That means to upgrade the line to four-track, straighten out some unnecessary curves, is relatively easy and cheap work, and thus the line speed can be upgraded.

The present length for a journey Glasgow to Euston, on the existing WCML, is timed at 4hrs. 30mins to 4hrs. 35 mins. . With these line improvements along its whole length the works would make it quite easy to reduce the time to under 4hrs, and even substantially further. May it be so.      

 

The ideas presented here for the Crewe to Manchester HS2 connection together with the improvements proposed for the WCML (together with additional new tracks) should make it quite clear that better solutions than the original HS2 exist. These can be implimented at a lower cost and most likely more easily. Without doubt the effect on the environment is lower and much less damaging. Let us hope the powers that be, put aside vainglorious ideas, and entreched attitudes and postures so as to come up with an acceptable, workable solution to the West Coast´s needs.